When does the EUDR apply to goods already in stock?

The application dates cut at placing on the market, not at production. Goods already placed on the EU market before the relevant date — 30 December 2026 for medium and large, 30 June 2027 for micro and small established as such by 31 December 2024, per Regulation (EU) 2025/2650 — are not re-caught by the regulation. Separately, the production date draws its own line: Products whose commodities were produced (for cattle: born) before 29 June 2023 are outside the EUDR (Art. 1(2)), and you must be able to prove the production date. Timber produced before that date stays under the EU Timber Regulation until 31 December 2029, then falls under the EUDR (Art. 37). Anything produced on or after 29 June 2023 and placed on the market from your application date needs full compliance.